6-4 BACKFILL ENVELOPE CONSTRUCTION
Backfill Placement
Storm sewers are sometimes placed on foundations that settle and shift
in a non-uniform manner. Fortunately, flexible pipe can accommodate many
of these changes without detrimental effects. The best construction practices,
however, involve placing the pipe on a firm foundation for maximum performance
and structural integrity throughout the design life.
In some cases it may be necessary to perform subsurface evaluations of
the soil conditions where muck, rock protrusions, or other unsuitable
conditions are suspected. Zones of soft material, such as muck, allow
the pipe to settle, potentially affecting the hydraulic characteristics
of the system. Rock protrusions apply point loads where they contact the
pipe that can affect the hydraulics or structural integrity of the system.
It is recommended that unsuitable foundation material be excavated before
installation of the pipe proceeds. Figure 6-1 illustrates how both soft
and rocky foundation materials should be dealt with before continuing
with the project.
Figure 6-1 Construction of Acceptable Foundation
If no undesirable foundation material is found, a few inches (approximately
0.05 - 0.15m) of bedding should be placed and compacted on the foundation
to equalize load distributions along the invert of the pipe. (Refer to
Figure 6-2 for a pictorial description of backfill terminology.) The bedding
can be shaped to conform to the outside of the pipe, although a more common
practice, especially for pipe 24" (600mm) and larger, is to place
the pipe on the bedding and carefully tamp or shovel the fill under the
haunches to the specified compaction level.
Figure 6-2 Typical Backfill Structure
The next layer of backfill, the haunching, is the most important since
it is this layer that provides the pipe with support against the soil
and traffic loadings. Haunching should be placed in lifts of about 4"
- 6" (0.10 - 0.15m) for optimum construction, or, as suggested in
Table 6-2, on both sides of the pipe. Tamp to achieve the specified compaction,
or shovel into the area, eliminating voids, if the material doesnt
require compaction. Construction of each lift should be repeated up to
the spring line.
Initial backfill extends from the spring line to a minimum of six inches
(0.15m) above the crown of the pipe. This area of the backfill anchors
the pipe and ensures that loads are distributed as evenly as possible
into the haunching. When using a material that requires compaction it
is important not to use mechanical compaction equipment directly on the
pipe itself.
Final backfill, which extends from the initial backfill layer to the
ground surface, does not directly support the pipe. For 4" - 48"
(100 - 1200mm) diameters the initial backfill shall be a minimum of six
inches (0.15m) and shall be a minimum of twelve inches (0.3m) for 54"
and 60" (1350mm and 1500mm) diameters. Proper compaction in this
area is not nearly so critical for the pipe as in the other layers. However,
if roads or drives will be crossing the pipe, a relatively high degree
of compaction is needed to prevent pavement settlement. In most installations
excavated materials will be of adequate quality for final backfill.
Flowable fill can be used as an alternative to compacted granular material,
however special precautions are necessary for a successful installation.
Flowable fill will cause the pipe to float or misalign. Therefore the
pipe will need to be weighted with sandbags or held with some type of
anchoring system. Alternatively, the flowable fill can be poured in layers
that are allowed to cure before the next layer is poured.
BACKFILL ENVELOPE CONSTRUCTION
|